CONSTRUCTION PROGRESS QUARTERLY REPORTQ2 AND Q3 2016

The Folly Road at Camp Road Intersection Improvements project on James Island involves improvements to Folly Road from approximately 1,000 feet south of Camp Road to the intersection with Eugene Gibbs Street and Rivers Point Row, and improvements to Camp Road from West Madison Avenue to Oyster Point Row. Construction started in Spring 2016 and is expected to continue through late 2017.

1PUBLIC OUTREACH

Groundbreaking Ceremony

Friday, March 18, 2016
Epworth United Methodist Church
Charleston, SC

30 ATTENDEES
Community Meeting

Thursday, April 14, 2016
Ft. Johnson Middle School
Charleston, SC

92 ATTENDEES
Business Meeting

Thursday, April 14, 2016
American Legion

11 ATTENDEES
Online Meeting
385 VISITORS = 10
James Island Public
Service Presentation

Monday, June 27, 2016

19 ATTENDEES
Resident mailings
3,775 SENT = 100
Business mailings
49 SENT

3PROGRESS

Initial pavement repairs on Folly Road

2070SQUARE YARDS OF FULL DEPTH PATCHING Phase I

Additional turn lanes added

0COMPLETE OF 7

Dual left turn lanes

0COMPLETE OF 1

Feet of bike lanes added

0COMPLETE OF 4,100 FT

Feet of sidewalks added

0COMPLETE OF 7,200 FT

Feet of drainage pipe

432COMPLETE OF 7,000 FT
2 of 2 water quality structures installed

Tons of pavement laid

1410TONS PLACED

Utilities relocated

50%COMPLETE OF 10 UTILITIES INVOLVED
SCE&G transmission complete

Traffic and pedestrian signals updated

0%

4FINANCIAL

Disadvantaged Business Enterprise Participation

3.4% COMPLETE OF INVOICED
Mandatory 13.5% of total construction contract; Mandatory 13.5% required due to federal funding rules

Small Business Enterprise Participation

1.6% OF TOTAL CONSTRUCTION CONTRACT
Mandatory SBE% is not allowed due to federal funding rules

$ Spent

$4.7M

5SCHEDULE

Phase 1

100% Complete

Start date: 3/20/2016
Completion date: 3/28/2016

Phase 2

35% Complete

Start date: 4/18/2016
Anticipated completion: Early 2017

Phase 3

0% Complete

Anticipated completion: Mid-2017

Phase 4

0% Complete

Anticipated completion: Late-2017

Phase 5

0% Complete

Anticipated completion: Late-2017