CONSTRUCTION PROGRESS QUARTERLY REPORTQ3 2017

Q3 2017
HIGHLIGHTS:

  • Utilities have made significant progress this quarter and are almost completely relocated throughout the project corridor.
  • The contractor is nearly complete with underground drainage installation.
  • Asphalt has been placed to raise the existing Folly Road to accommodate the installation of widening areas.
  • The road elevation is being raised to aid in the drainage of Folly Road to prevent future flooding issues

2PROGRESS

Initial pavement repairs on Folly Road

2070SQUARE YARDS OF FULL DEPTH PATCHING Phase I

Additional turn lanes added

0COMPLETE OF 7

Dual left turn lanes

0COMPLETE OF 1

Feet of bike lanes added

0COMPLETE OF 4,100 FT

Feet of sidewalks added

5432COMPLETE OF 7,200 FT

Feet of drainage pipe

6569COMPLETE OF 7,300 FT
2 of 2 water quality structures installed

Tons of pavement laid

5888TONS PLACED

Utilities relocated

95%COMPLETE
SCE&G transmission complete

Traffic and pedestrian signals updated

75%COMPLETE
Mast Arm foundations installed

3FINANCIAL

Disadvantaged Business Enterprise Participation

11.3% COMPLETE OF INVOICED
Mandatory 13.5% of total construction contract; Mandatory 13.5% required due to federal funding rules

Small Business Enterprise Participation

4.5% OF TOTAL CONSTRUCTION CONTRACT
Mandatory SBE% is not allowed due to federal funding rules

$ Spent

$9.5M

4SCHEDULE

Phase 1

100% Complete

Start date: 3/20/2016
Completion date: 3/28/2016

Phase 2

75% Complete

Start date: 4/18/2016
Anticipated completion: Mid-2017

Phase 3

75% Complete

Anticipated completion: Mid-2017

Phase 4

60% Complete

Anticipated completion: Late-2017

Phase 5

0% Complete

Anticipated completion: Early-2018